§ 58-186. Change orders.


Latest version.
  • Change orders to contracts under the supervision of the public works department previously approved by the proper village authorities may be allowed, executed and approved by the designated engineer and either the public works director, the village president or the village administrator for an amount not to exceed $5,000.00, and all change orders in excess of $5,000.00 shall require prior board approval. Upon the approval of the change order by the proper parties under this section, written notification must be submitted to the board of trustees within 48 hours after the execution of such change order. The failure to submit the change order to the board of trustees within 48 hours after the execution of the change order may result in the disapproval of the change order.

(Ord. No. 2016-01, § 2, 1-5-2016)